Karlsruhe

New construction center

Quality assurance in supply engineering for a computer centre with the highest requirements for supply security
Quality assurance in the trades electrical engineering, refrigeration technology and building automation from the plan review to the inspection of the construction of an underground data processing centre with 6,600 m² IT space. With eight fully redundantly supplied IT modules with a total electrical connected load of 22 MW, 11 MW electrical power is available for active IT components. A total cooling capacity of 15 MW is installed for the full extension.
Share article

Project data

Object details:
Underground data processing centre with 8 IT modules for full IT service for banks and cooperative companies
Client:
FIDUCIA GAD IT AG
GFA:
14.000 m2

Provided services

Manage

Project management
Photo:
© gorodenkoff – iStock